Load Test of a Power Station
Posted by Tom Lau on
The customer entrusted our company to provide special technical services for the rental of high-voltage capacitors for the load protection polarity verification project of the 220kV booster station of the power plant.
The goal of the technical service: to complete the load protection polarity verification of the 220kV booster station of the Jiangyin gas turbine power plant.
The content of the technical service: to provide a load of 18MVA capacity.
Project progress:
1. On-site survey. Confirm the placement of on-site equipment and the layout of cable routing.
2. Equipment entry. Arrange the crane to unload in the designated area.
The equipment includes 4 transformers (6.3KV to 440V), 4 6MVA load boxes, and several low-voltage cables and high-voltage cables.
3. Cable connection. Connect the power supply and load equipment according to the customer's wiring requirements.
4. Simulated load test. After all cables are connected, test the function first, and then wait for the client to notify the power supply and load.